Starting on the wiring.



Sorting at the wiring and gauges, and looking at the side impact structure. Not so much that I have it 100% completed before I move on, but to make sure it fits. The rear hub bearing carriers are something that I might send out. Not sure if I have the proper equipment or knowledge to rebuild them? But should make a decision soon.

Monday, December 1, 2008

Right side done.

Right front went together without a hitch.

Sunday, November 30, 2008

That's the problem.

As mentioned in a earlier post, the steering geometry didn't seem correct. I discovered my error when assembling the right side. The two aluminum plates that mount on the bearing carrier where placed upside down. I assumed the aluminum triangle was equal distance, but I was wrong. Steering rack, toe links all look right now. So I guess I'm going back to the photos and place the spacers on the bottom.
The plate on the top is correct.

Friday, November 28, 2008

Plating and more.

Finishing up the plating for the right front suspension and should be assembled today.

Monday, November 17, 2008

Now for the right side


Everything looks good. Seems to be plenty of clearance. The right side should go faster, now that I know the pitfalls. The goal is to have everything forward of the roll bar completed by year's end.

Sunday, November 16, 2008

Photos ???

I've probably mentioned this before, but the car was completely dismantled and later, reassembled to sell but never raced. So all the photos and notes taken might not be accurate. This is a issue I came across on the spacers used on the steering link that connects to the front bearing carrier. The old photos shows the spacer on the bottom. When connected there, it just throws everything off, and looking at photos of other Lola T190's 92's, it shows the spacer on the top, which works better. So for now I'm placing it on the top. When the right side suspension is on, I'll have a better idea. I think the bump steer is through these spacers? It's been awhile.

Sunday, November 9, 2008

Front Suspension

Starting to place some of the front suspension hardware on the car. Temporary put in place just to make sure it all bolts together properly.

Thursday, November 6, 2008

Rotor Time.

It's back to work. Pulled out the left front rotor from my boxes of many parts. Another one of those parts you forget about and realize it has to be inspected and cleaned up., and there's 3 more to do. Starting to think I better pickup the pace a bit, if I want to race next year.

Saturday, November 1, 2008

12" Snow in October?

Tuesday looked like a tornado past through. The snow stuck to the leaves and just broke everything. The power to the house went out at noon on Tuesday and return late Thursday evening. However the shop where I keep the car is behind the house and has a separate electric line. Tree snapped it and now I'm still waiting for electric back there.

Monday, October 27, 2008

Fuel cells, steering rack.

Steering rack is installed, fuel cells front crossover plumbing all connected.

Can closeup the fuel cells now, and move to the left front suspension.

Monday, October 20, 2008

More Progress

Last week was productive. Clutch line is done, steering rack is ready for installation and gas, brake and clutch pedals are in and tight. Waiting on some hardware from "Pegasus" and "Air Craft Spruce".

Sunday, October 12, 2008

Decals

It's starting to come together. But, as with everything else, it sure has taken a lot longer to accomplished.

Monday, October 6, 2008

I'm changing the route the left rear brake line takes. The old line went around the radiator cooling line(photo). The new line will stay along the tub, hoping this stays out of the way of parts, down the road. I purchased the car as a roller, so I have not photos of the car complete in this area.



Saturday, October 4, 2008

Fuel cells and lines.


This week has been fairly productive. I did have to make a small adjustment to the front brake lines. I forgot the square radiator cooling lines run down the same channel as the brake lines and had to move the lines to the side. No big deal but still took a couple of hours. Before I tackle the rear lines I’ll take a real close look at my photos of this section and try to get it right the first time.
As you can see the fuel cells are installed. As mention in a earlier blog, make small modifications to the tub to accept the new cells. But they went right in on the first try, and fit perfect.

Monday, September 29, 2008

Brake Lines

Didn't think I would have anytime today for the car, but found about a hour and got the front brake lines done.