Fuel cells, steering rack.

Steering rack is installed, fuel cells front crossover plumbing all connected.

Can closeup the fuel cells now, and move to the left front suspension.

Monday, October 20, 2008

More Progress

Last week was productive. Clutch line is done, steering rack is ready for installation and gas, brake and clutch pedals are in and tight. Waiting on some hardware from "Pegasus" and "Air Craft Spruce".

Sunday, October 12, 2008

Decals

It's starting to come together. But, as with everything else, it sure has taken a lot longer to accomplished.

Monday, October 6, 2008

I'm changing the route the left rear brake line takes. The old line went around the radiator cooling line(photo). The new line will stay along the tub, hoping this stays out of the way of parts, down the road. I purchased the car as a roller, so I have not photos of the car complete in this area.



Saturday, October 4, 2008

Fuel cells and lines.


This week has been fairly productive. I did have to make a small adjustment to the front brake lines. I forgot the square radiator cooling lines run down the same channel as the brake lines and had to move the lines to the side. No big deal but still took a couple of hours. Before I tackle the rear lines I’ll take a real close look at my photos of this section and try to get it right the first time.
As you can see the fuel cells are installed. As mention in a earlier blog, make small modifications to the tub to accept the new cells. But they went right in on the first try, and fit perfect.